Sl.No. Name of Work & Location Division Total Work Value
in INR Millions
1 OB Removal work at Bina OCP of NCL. Northern Coalfields Limited 4532.36
2 OB Removal work at Gouthamkhani OCP, Kothagudem Area. The Singareni Collieries Company Limited 1745.50
3 OB Removal work at Nigahi OCP of NCL. Dilip Buildcon Ltd 11802.42
4 Overburden Removal work at Medapalli OCP, RG-I Area The Singareni Collieries Company Limited 5071.48
5 Hiring of Plant & Mining Machineries for working in Kumaraswamy Iron Ore Mine. NMDC 1194.10
6 Overburden Removal work at AMLOHRI OCP of NCL. Northern Coalfields Limited 1524.31
7 Overburden Removal work at West Section of JAYANT OCP of NCL. Northern Coalfields Limited 7786.56
8 Overburden Removal work at DUDHICHUA OCP of NCL. Northern Coalfields Limited 1221.64
9 Overburden Removal work at JAYANT OCP of NCL. Northern Coalfields Limited 1729.32
10 Extraction of 46.272 LBCM of coal/shale with Surface Miner, including Loading, Transportation, Dumping etc., at Pit-III of Koyagudem OCP-II, Yellandu area. The Singareni Collieries Co Ltd, Telangana 435.02
11 Overburden Removal work at Koyagudem OCP, Yellandu Area. The Singareni Collieries Co Ltd, Telangana 1338.63
12 Blast hole drilling, controlled blasting with shock tube initiation, excavation, loading Transportation and dumping etc, of Overburden at Srirampur OCP, Srirampur Area. The Singareni Collieries Co Ltd, Telangana 6312.30

Sl.No. Name of Work & Location Division Total Work Value in INR Millions
1 Earth work excavation of approach channel, Pump house area and gravity canal near Annaram Lift system of Kaleshwaram Project (New) Megha Engineering & Infrastructures Ltd, Karimnagar, Telangana 600.00
2 Construction of Earth work, C.C lining & various Structures of Mokhabardi Main Canal from Km.0.00 to 23.85 Km of Mokhabardi Lift Irrigation Scheme. (VPR Mining Share - 70%) Ambhora Lift Irrigation Division,Bhiwapur, Maharastra 1044.33
3 GNSS - Excavation of GNSS Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD work from km 16.500 to km 34.800/32.520 in Kurnool and Kadapa Districts Package - 48 (VPR Share-50%). Irrigation & CAD Department, Nandyal, Andhra Pradesh 3441.67
4 GNSS - Excavation of GNSS Flood Flow Canal from Owk Reservoir to Gandikota Reservoir including construction of CM & CD work from km 34.800 to km 52.875/52.184 in Kadapa District Package - 49 (VPR Share-50%). Irrigation & CAD Department, Nandyal, Andhra Pradesh 3246.65
5 Construction of Earth Work and Structures in Km.11 to 20 of Deoli Branch Canal of Lower Wardha Project. EE, Lower Wardha Canal Division , Wardha (Pipri), Maharashtra 2071.23